Action Plans
Consolidated mitigation & audit recommendation tracker — live-linked dengan Risk Register & Audit Findings
401 action plans
| Source | Reference | Action / Recommendation | PIC | Due Date | Progress | Status | Update |
|---|---|---|---|---|---|---|---|
| Audit | AF-2025-012 | Evaluasi pengendalian: Kehilangan cadangan tambang | Sr Business Development Specialist | 2025-01-28 | 60% | In Progress | |
| Audit | AF-2025-024 | Evaluasi pengendalian: Keterlambatan sparepart | Plant & Maintenance Section Head | 2025-01-28 | 60% | In Progress | |
| Audit | AF-2025-036 | Evaluasi pengendalian: Kesalahan sampling | Reclamation, Post Mining, & QMS Department Head | 2025-01-28 | 60% | In Progress | |
| Audit | AF-2025-048 | Evaluasi pengendalian: Penurunan rating ESG | CSR/Community Development Section Head | 2025-01-28 | 60% | In Progress | |
| Audit | AF-2025-013 | Evaluasi pengendalian: Ketergantungan pada satu buyer | Sr Business Development Specialist | 2025-02-28 | 60% | In Progress | |
| Audit | AF-2025-025 | Evaluasi pengendalian: Kecelakaan alat berat | Plant & Maintenance Section Head | 2025-02-28 | 60% | In Progress | |
| Audit | AF-2025-037 | Evaluasi pengendalian: Pelanggaran RKAB | Government Relation Section Head | 2025-02-28 | 60% | In Progress | |
| Audit | AF-2025-014 | Evaluasi pengendalian: Akuisisi atau investasi yang gagal | Sr Business Development Specialist | 2025-03-28 | 10% | Open | |
| Audit | AF-2025-026 | Evaluasi pengendalian: Kekurangan unit produksi | Plant & Maintenance Section Head | 2025-03-28 | 10% | Open | |
| Audit | AF-2025-038 | Evaluasi pengendalian: Pelanggaran lingkungan | Government Relation Section Head | 2025-03-28 | 10% | Open | |
| Audit | AF-2025-015 | Evaluasi pengendalian: Reputasi perusahaan buruk | Sr Business Development Specialist | 2025-04-28 | 60% | In Progress | |
| Audit | AF-2025-027 | Evaluasi pengendalian: Kinerja kontraktor buruk | Engineering Section Head | 2025-04-28 | 60% | In Progress | |
| Audit | AF-2025-039 | Evaluasi pengendalian: Keterlambatan pembayaran royalti | Government Relation Section Head | 2025-04-28 | 60% | In Progress | |
| Audit | AF-2025-016 | Evaluasi pengendalian: Konflik dengan pemegang saham | Sr Business Development Specialist | 2025-05-28 | 60% | In Progress | |
| Audit | AF-2025-028 | Evaluasi pengendalian: Kontraktor mengalami masalah keuangan | Engineering Section Head | 2025-05-28 | 60% | In Progress | |
| Audit | AF-2025-040 | Evaluasi pengendalian: Pelanggaran K3 | Government Relation Section Head | 2025-05-28 | 60% | In Progress | |
| Audit | AF-2025-017 | Evaluasi pengendalian: Risiko geopolitik global | Sr Business Development Specialist | 2025-06-28 | 10% | Open | |
| Audit | AF-2025-029 | Evaluasi pengendalian: Pelanggaran HSE oleh kontraktor | Engineering Section Head | 2025-06-28 | 10% | Open | |
| Audit | AF-2025-041 | Evaluasi pengendalian: Risiko kurs USD-IDR | Finance AP & Banking Section Head | 2025-06-28 | 10% | Open | |
| Audit | AF-2025-018 | Evaluasi pengendalian: Longsor highwall/pit wall failure | Production Section Head | 2025-07-28 | 60% | In Progress | |
| Audit | AF-2025-030 | Evaluasi pengendalian: Jalan hauling rusak | Port Operation Section Head | 2025-07-28 | 60% | In Progress | |
| Audit | AF-2025-042 | Evaluasi pengendalian: Risiko likuiditas | Finance AP & Banking Section Head | 2025-07-28 | 60% | In Progress | |
| Audit | AF-2025-019 | Evaluasi pengendalian: Banjir tambang | Production Section Head | 2025-08-28 | 60% | In Progress | |
| Audit | AF-2025-031 | Evaluasi pengendalian: Kecelakaan hauling | Port Operation Section Head | 2025-08-28 | 60% | In Progress | |
| Audit | AF-2025-043 | Evaluasi pengendalian: Risiko piutang buyer | Finance AP & Banking Section Head | 2025-08-28 | 60% | In Progress | |
| Audit | AF-2025-002 | Kewajiban pelaporan ke regulator terlambat | Government Relation Section Head | 2025-08-31 | 10% | Open | |
| Audit | AF-2025-005 | Frekuensi pemantauan kualitas air di bawah RKL-RPL | Health, Safety & Environment Department Head | 2025-09-15 | 60% | In Progress | |
| Audit | AF-2025-008 | Evaluasi pengendalian: Penurunan harga batubara global | Sr Business Development Specialist | 2025-09-28 | 10% | Open | |
| Audit | AF-2025-020 | Evaluasi pengendalian: Kegagalan disposal | Production Section Head | 2025-09-28 | 10% | Open | |
| Audit | AF-2025-032 | Evaluasi pengendalian: Gangguan pelabuhan | Port Operation Section Head | 2025-09-28 | 10% | Open | |
| Audit | AF-2025-044 | Evaluasi pengendalian: Risiko kenaikan BBM | Finance AP & Banking Section Head | 2025-09-28 | 10% | Open | |
| Audit | AF-2025-001 | SOP penambangan belum diterapkan konsisten di lapangan | Production Section Head | 2025-09-30 | 60% | In Progress | |
| Audit | AF-2025-003 | Prosedur sampling batubara belum sesuai standar | Production Section Head | 2025-10-15 | 60% | In Progress | |
| Audit | AF-2025-009 | Evaluasi pengendalian: Perubahan regulasi pemerintah | Sr Business Development Specialist | 2025-10-28 | 60% | In Progress | |
| Audit | AF-2025-021 | Evaluasi pengendalian: Cadangan tidak sesuai model geologi | Production Section Head | 2025-10-28 | 60% | In Progress | |
| Audit | AF-2025-033 | Evaluasi pengendalian: Cuaca ekstrem | Port Operation Section Head | 2025-10-28 | 60% | In Progress | |
| Audit | AF-2025-045 | Evaluasi pengendalian: Konflik masyarakat | CSR/Community Development Section Head | 2025-10-28 | 60% | In Progress | |
| Audit | AF-2025-006 | Review hak akses sistem belum dilakukan berkala | IT Department Head | 2025-10-31 | 60% | In Progress | |
| Audit | AF-2025-010 | Evaluasi pengendalian: Kebijakan DMO dan HBA | Sr Business Development Specialist | 2025-11-28 | 60% | In Progress | |
| Audit | AF-2025-022 | Evaluasi pengendalian: Kualitas batubara tidak sesuai spesifikasi | Production Section Head | 2025-11-28 | 60% | In Progress | |
| Audit | AF-2025-034 | Evaluasi pengendalian: Self combustion | Reclamation, Post Mining, & QMS Department Head | 2025-11-28 | 60% | In Progress | |
| Audit | AF-2025-046 | Evaluasi pengendalian: Kegagalan reklamasi | CSR/Community Development Section Head | 2025-11-28 | 60% | In Progress | |
| Audit | AF-2025-004 | Dokumentasi realisasi program CSR belum lengkap | CSR/Community Development Section Head | 2025-11-30 | 60% | In Progress | |
| Audit | AF-2025-007 | Realisasi training plan di bawah target tahunan | HC Strategic & Development Department Head | 2025-12-15 | 60% | In Progress | |
| Audit | AF-2025-011 | Evaluasi pengendalian: Transisi energi (ESG & Net Zero) | Sr Business Development Specialist | 2025-12-28 | 10% | Open | |
| Audit | AF-2025-023 | Evaluasi pengendalian: Breakdown alat utama | Plant & Maintenance Section Head | 2025-12-28 | 10% | Open | |
| Audit | AF-2025-035 | Evaluasi pengendalian: Kontaminasi batubara | Reclamation, Post Mining, & QMS Department Head | 2025-12-28 | 10% | Open | |
| Audit | AF-2025-047 | Evaluasi pengendalian: Isu HAM dan tenaga kerja | CSR/Community Development Section Head | 2025-12-28 | 10% | Open | |
| Risk | FU-0108RR-0160 | Melakukan block account Administrator user untuk melakukan instal applikasi sendiri. User tidak bisa melakukan instal/uninstal tanpa ada pendampingan dari team IT. Serta penutupan jalur data USB pada laptop User. | IT Department Head | 2026-01-22 | 100% | Closed | |
| Risk | FU-0179RR-0231 | Pemetaan ulang lahan belum bebas & negosiasi terjadwal dengan pemilik lahan | Land Acquisition & CSR Section Head | 2026-01-22 | 10% | Progress | |
| Risk | FU-0092RR-0144 | Follow up kepada tim engineering dan manajemen terkait percepatan pemenuhan fleet sesuai plan yang telah disepakati di JSO | Short Term Mine Planning Section Head | 2026-01-27 | 100% | Closed | |
| Risk | FU-0163RR-0215 | Penyusunan ESG roadmap & sustainability report untuk memenuhi ekspektasi lender dan investor | Finance AP & Banking Section Head | 2026-01-27 | 10% | Progress | |
| Risk | FU-0037RR-0037 | Monitoring RKAB berkala | Government Relation Section Head | 2026-01-30 | 10% | Open | |
| Risk | FU-0146RR-0198 | Penambahan kapasitas pompa dewatering, penyiapan sump berjenjang dan rencana mining sequence musim hujan | Mining Production Section Head | 2026-01-30 | 10% | Progress | |
| Risk | FU-0009RR-0009 | Regulatory monitoring, stakeholder engagement, legal review berkala | Sr Business Development Specialist | 2026-02-03 | 10% | Open | |
| Risk | FU-0010RR-0010 | Optimalisasi cost structure, diversifikasi produk dan pasar ekspor | Sr Business Development Specialist | 2026-02-04 | 10% | Continue | |
| Risk | FU-0051RR-0103 | Bekerja sama dengan lembaga berwenang untuk penertiban lahan HIdayat | Government Relation & Legal Section Head | 2026-02-04 | 10% | Open | |
| Risk | FU-0069RR-0121 | Dilakukan evaluasi kembali terkait rencana reklamasi dan progress STL | Reclamation, Post Mining, & Quality Management System Department Head | 2026-02-04 | 10% | Progress | |
| Risk | FU-0069-2RR-0121 | Dilakukan evaluasi kembali terkait rencana reklamasi dan progress STL | Reclamation, Post Mining, & Quality Management System Department Head | 2026-02-04 | 10% | Open | |
| Risk | FU-0091RR-0143 | Monitoring dan evaluasi PA, UA, produktivitas, dan populasi unit produksi dan pemompaan PT HRS | Short Term Mine Planning Section Head | 2026-02-05 | 10% | Open | |
| Risk | FU-0158RR-0210 | Program fuel efficiency: pengaturan idle time, tune-up engine dan pemantauan konsumsi per unit | Plant & Maintenance Section Head | 2026-02-05 | 10% | Progress | |
| Risk | FU-0130RR-0182 | Pelaporan status karhutla & koordinasi dengan KLHK, BPBD dan Dinas Kehutanan untuk mitigasi sanksi | Government Relation Section Head | 2026-02-12 | 10% | Progress | |
| Risk | FU-0054RR-0106 | Melakukan penyiraman berkala di area ROM BSSR | Port Operation Section Head | 2026-02-13 | 100% | Closed | |
| Risk | FU-0101RR-0153 | Membuat flow process (SOP) terkait penanganan medis di area mess serta melakukan analisa untuk penunjukan Klinik / RS / Dokter rekanan terdekat untuk keadaan emergency. | Safety & Health Section Head | 2026-02-13 | 10% | Open | |
| Risk | FU-0067RR-0119 | Rencana aksi yang akan dilakukan untuk memitigasi risiko ketidaksesuaian rencana post mining Area Bara 678 dengan RTRW IKN dimulai dengan melakukan review internal terhadap dokumen perencanaan yang ada dan membandingkannya dengan ketentuan tata ruang terbaru. Selanjutnya, dilakukan diskusi dan konsultasi dengan tim legal serta tim perizinan untuk memastikan aspek regulasi dan kepatuhan telah terpenuhi. Perusahaan juga akan melakukan koordinasi dan audiensi dengan Otorita IKN guna memperoleh arahan dan klarifikasi terkait kemungkinan penyesuaian atau alternatif pemanfaatan lahan pascatambang. Berdasarkan hasil pembahasan tersebut, dokumen rencana post mining akan direvisi dan disesuaikan agar selaras dengan RTRW, kemudian diajukan kembali sesuai prosedur yang berlaku, serta dilakukan monitoring berkala terhadap perkembangan kebijakan tata ruang. | Reclamation, Post Mining, & Quality Management System Department Head | 2026-02-16 | 100% | Closed | |
| Risk | FU-0026RR-0026 | Fleet planning dan contractor backup | Plant & Maintenance Section Head | 2026-02-17 | 10% | Continue | |
| Risk | FU-0044RR-0044 | Fuel efficiency program | Finance AP & Banking Section Head | 2026-02-18 | 10% | Progress | |
| Risk | FU-0003RR-0003 | Penguatan QA/QC sampling & kontrol blending stockpile | Production Section Head | 2026-02-23 | 10% | Progress | |
| Risk | FU-0072RR-0124 | Menunggu hingga bulan Agustus, apabila sampai Agustus tidak ada hujan maka per September akan dilakukan treatment penyiraman. Diskusi lebih lanjut dengan tim reklamasi dan kontraktor (terkait additional) : apakah menggunakan dump truk, selang, atau metode lain. | Reclamation, Post Mining, & Quality Management System Department Head | 2026-02-24 | 10% | Open | |
| Risk | FU-0102RR-0154 | Membuat perhitungan pemakaian solar dan fuel trap | Safety & Health Section Head | 2026-02-24 | 100% | Closed | |
| Risk | FU-0102-2RR-0154 | Membuat sistem pengisian langsung dari FT ke Tanki sementara Mega Injeksi | Safety & Health Section Head | 2026-02-24 | 100% | Closed | |
| Risk | FU-0031RR-0031 | Traffic management plan | Port Operation Section Head | 2026-02-25 | 100% | Closed | |
| Risk | FU-0023RR-0023 | Preventive maintenance dan predictive maintenance | Plant & Maintenance Section Head | 2026-02-26 | 100% | Closed | |
| Risk | FU-0041RR-0041 | Natural hedge dan hedging | Finance AP & Banking Section Head | 2026-02-26 | 10% | Open | |
| Risk | FU-0143RR-0195 | Penambahan frekuensi water truck pada jalan hauling melewati pemukiman & pemasangan rambu batas kecepatan | Hauling Section Head | 2026-02-26 | 10% | Progress | |
| Risk | FU-0114RR-0166 | Evaluasi kajian enviro apakah terdapat Creek lain yang menyebabkan lahan karet yang diklaim tergenang, serta melakukan monitoring kualitas air yang masuk | Government Relation Section Head | 2026-02-27 | 10% | Progress | |
| Risk | FU-0114-2RR-0166 | Tim Engineering melakukan kajian terkait area dumping disposal, apakah benar berdampak dengan area Lahan Karet yang diklaim (jarak Disposal ke Lahan 500 meter) | Government Relation Section Head | 2026-02-27 | 10% | Progress | |
| Risk | FU-0185RR-0237 | Penjadwalan ulang penanaman mengikuti musim, penambahan nursery lokal dan monitoring tumbuh tanaman | Reclamation Section Head | 2026-02-27 | 10% | Progress | |
| Risk | FU-0093RR-0145 | Melakukan koordinasi dengan tim lahan secara weekly | Short Term Mine Planning Section Head | 2026-03-02 | 100% | Closed | |
| Risk | FU-0148RR-0200 | Peningkatan elevasi jalan kritis, perbaikan gorong-gorong dan paritan aliran air | Civil Engineering & Infrastructure Section Head | 2026-03-02 | 10% | Progress | |
| Risk | FU-0060RR-0112 | Melakukan kontrol operasional terhadap volume tonase yang masuk ke stockpile | Production Section Head | 2026-03-09 | 100% | Closed | |
| Risk | FU-0082RR-0134 | Melakukan improve kenaikan harga upah angkut berdasarkan perhitungan ICI terbaru dan Harga dasar solar terbaru (Fuel Price Adjustment) | CPP & Road Maintenance Section Head | 2026-03-09 | 100% | Closed | |
| Risk | FU-0175RR-0227 | Protokol kesehatan kerja, vaksinasi karyawan dan kerja sama rumah sakit rujukan | HCGA Section Head | 2026-03-09 | 10% | Progress | |
| Risk | FU-0109RR-0161 | Penambahan arester terminal untuk meminimalisir induksi petir masuk ke jaringan listrik server | IT Department Head | 2026-03-10 | 100% | Closed | |
| Risk | FU-0118RR-0170 | Memperpendek interval penggantian part fuel separator dari 250 jam menjadi 150 jam | Plant & Maintenance Section Head | 2026-03-10 | 100% | Closed | |
| Risk | FU-0118-2RR-0170 | Pengadaan filter separator fuel modul dengan mikron yang lebih kecil agar endapan/gel dapat tersaring dengan maksimal | Plant & Maintenance Section Head | 2026-03-10 | 100% | Closed | |
| Risk | FU-0137RR-0189 | Renegosiasi jadwal shipment dengan buyer dan penyesuaian klausul force majeure kontrak penjualan | Sales Operation Section Head | 2026-03-10 | 10% | Progress | |
| Risk | FU-0153RR-0205 | Cash flow stress test, pengetatan capex non-esensial dan penyediaan fasilitas kredit siaga | Finance AP & Banking Section Head | 2026-03-10 | 10% | Progress | |
| Risk | FU-0180RR-0232 | Kajian struktur bangunan kritikal, penyusunan emergency response plan bencana alam dan drill berkala | Civil Engineering & Infrastructure Section Head | 2026-03-10 | 10% | Progress | |
| Risk | FU-0034RR-0034 | Temperature monitoring | Reclamation, Post Mining, & QMS Department Head | 2026-03-18 | 10% | Continue | |
| Risk | FU-0008RR-0008 | Diversifikasi pasar, kontrak jangka panjang, hedging harga | Sr Business Development Specialist | 2026-03-20 | 10% | Progress | |
| Risk | FU-0011RR-0011 | Diversifikasi bisnis energi, investasi hilirisasi dan renewable energy | Sr Business Development Specialist | 2026-03-20 | 100% | Closed | |
| Risk | FU-0070RR-0122 | Perlunya dilakukan kajian geoteknik di area patahan bank soil BARA 7 untuk memitigasi pergerakan longsoran | Reclamation, Post Mining, & Quality Management System Department Head | 2026-03-20 | 10% | Progress | |
| Risk | FU-0107RR-0159 | Adanya backup jaringan menggunakan radio jaringan komunikasi agar jaringan tetap terhubung selama dilakukannya penyambungan fiber optic yang putus. | IT Department Head | 2026-03-20 | 10% | Open | |
| Risk | FU-0088RR-0140 | Follow UP perizinan PERTEK ke KLHK | Short Term Mine Planning Section Head | 2026-03-23 | 10% | Open | |
| Risk | FU-0159RR-0211 | Monitoring regulasi ESDM/Kemenkeu, gap analysis kepatuhan dan penyesuaian prosedur internal | Government Relation Section Head | 2026-03-23 | 10% | Progress | |
| Risk | FU-0177RR-0229 | Penertiban bersama lembaga berwenang dan penguatan patroli batas konsesi | Land Acquisition & CSR Section Head | 2026-03-27 | 10% | Progress | |
| Risk | FU-0131RR-0183 | Pengaturan shift & penghentian sementara aktivitas saat visibilitas < 50 m, penambahan tower lamp dan rambu reflektif | Mining Production Section Head | 2026-03-30 | 10% | Progress | |
| Risk | FU-0186RR-0238 | Review kecukupan jaminan reklamasi & konsistensi dokumen rencana pascatambang | Technical Services Section Head | 2026-03-30 | 10% | Progress | |
| Risk | FU-0014RR-0014 | Due diligence komprehensif dan post-merger integration plan | Sr Business Development Specialist | 2026-03-31 | 10% | Continue | |
| Risk | FU-0100RR-0152 | Melakukan identifikasi terkait progress reklamasi untuk seluruh Blok AGM. Melakuan evaluasi terkait productivity reklamasi. | Safety & Health Section Head | 2026-03-31 | 10% | Progress | |
| Risk | FU-0066RR-0118 | Plan replace shaft dan bearing head feeder | Plant & Maintenance Section Head | 2026-04-02 | 100% | Closed | |
| Risk | FU-0029RR-0029 | Audit HSE dan induction ketat | Engineering Section Head | 2026-04-03 | 10% | Open | |
| Risk | FU-0087RR-0139 | Monitoring PA unit loader dan hauler PT HRS | Short Term Mine Planning Section Head | 2026-04-03 | 10% | Progress | |
| Risk | FU-0087-2RR-0139 | Penyampaian kepada tim engineering dan manajemen site PT HRS agar dapat memenuhi populasi unit running sesuai dengan plan JSO yang telah disepakati | Short Term Mine Planning Section Head | 2026-04-03 | 10% | Progress | |
| Risk | FU-0002RR-0002 | Penyusunan compliance calendar & pemenuhan kewajiban PNBP/RKAB | Government Relation Section Head | 2026-04-08 | 10% | Progress | |
| Risk | FU-0105RR-0157 | Melakukan weekly meeting untuk memastikan progress project Pengalihan Jalan Aspal Kabupaten PIT A Blok 2 Sepanjang 1 km | Civil Engineering & Infrastructure Section Head | 2026-04-09 | 10% | Progress | |
| Risk | FU-0105-2RR-0157 | Proses pembebasan lahan area Pengalihan Jalan Aspal Kabupaten PIT B Blok 2 sudah dimulai dan harus selesai 100% sebelum Juni 2026 | Civil Engineering & Infrastructure Section Head | 2026-04-09 | 10% | Progress | |
| Risk | FU-0105-3RR-0157 | Proses pengajuan budget melalui CRF sudah diajukan per 3 Maret 2026 harus sudah approved maksimal pada 20 April 2026 | Civil Engineering & Infrastructure Section Head | 2026-04-09 | 100% | Closed | |
| Risk | FU-0105-4RR-0157 | Proses perijinan tukar menukar BMD (Barang Milik Daerah) Jalan Kabupaten sudah dimulai dan selesai pada 31 Desember 2026 | Civil Engineering & Infrastructure Section Head | 2026-04-09 | 10% | Progress | |
| Risk | FU-0055RR-0107 | loading time Tidak mencapai target KPI 1,450 MT/Jam | Port Operation Section Head | 2026-04-10 | 100% | Closed | |
| Risk | FU-0073RR-0125 | Melakukan validasi part number barang yang dibutuhkan | Procurement Section Head | 2026-04-10 | 100% | Closed | |
| Risk | FU-0142RR-0194 | Penjadwalan penanaman mengikuti prakiraan musim BMKG dan penyiraman terjadwal untuk bibit reklamasi | Reclamation, Post Mining, & Quality Management System Department Head | 2026-04-13 | 10% | Progress | |
| Risk | FU-0022RR-0022 | Quality control dan blending management | Production Section Head | 2026-04-14 | 10% | Continue | |
| Risk | FU-0040RR-0040 | SMKP Minerba | Government Relation Section Head | 2026-04-14 | 10% | Progress | |
| Risk | FU-0115RR-0167 | Sudah dilakukan koordinasi dengan pemerintah desa terkait dan saat ini tim Enviro sedang melakukan kajian aliran yang keluar dari AGM dan berpotensi pencemaran | Government Relation Section Head | 2026-04-14 | 10% | Progress | |
| Risk | FU-0151RR-0203 | SOP penghentian loading pada gelombang di atas batas aman dan pengikatan tongkang tambahan | Port Operation Section Head | 2026-04-15 | 10% | Progress | |
| Risk | FU-0007RR-0007 | Program training & succession planning untuk posisi kunci | HC Strategic & Development Department Head | 2026-04-17 | 10% | Open | |
| Risk | FU-0134RR-0186 | Distribusi masker N95 dan pemeriksaan kesehatan pekerja area terdampak asap | Safety & Health Section Head | 2026-04-20 | 10% | Progress | |
| Risk | FU-0139RR-0191 | Pembangunan embung/reservoir cadangan air dan jaringan distribusi air site | Civil Engineering & Infrastructure Section Head | 2026-04-22 | 10% | Progress | |
| Risk | FU-0063RR-0115 | Plan Under Carriage replacement, berkoordinasi dengan vendor dan Supply Chain Department untuk pengadaan Part Under Caariage | Plant & Maintenance Section Head | 2026-04-23 | 100% | Closed | |
| Risk | FU-0081RR-0133 | Melakukan koordinasi dengan tim SC terkait permintaan rental TW 20 KL tersebut | CPP & Road Maintenance Section Head | 2026-04-23 | 100% | Closed | |
| Risk | FU-0110RR-0162 | Proses timbangan akan manual saat jaringan di area timbangan down | IT Department Head | 2026-04-23 | 100% | Closed | |
| Risk | FU-0174RR-0226 | Fogging berkala, sanitasi camp, penyediaan klinik site dan pemeriksaan kesehatan rutin | Safety & Health Section Head | 2026-04-23 | 10% | Progress | |
| Risk | FU-0125RR-0177 | melakukan alternative sourcing di vendor lokal yang dapat menyediakan sparepart dengan status Lartas di Dealer | Warehouse & Logistic Section Head | 2026-04-24 | 10% | Open | |
| Risk | FU-0125-2RR-0177 | Optimalisasi pengadaan lokal dilakukan melalui identifikasi part OEM yang tersedia di pasar domestik, terutama untuk kategori non-essential spare part, dengan substitusi ke part umum yang memiliki spesifikasi teknis setara seperti bolt, nut, dan washer. | Warehouse & Logistic Section Head | 2026-04-24 | 100% | Closed | |
| Risk | FU-0152RR-0204 | Diversifikasi buyer & pasar tujuan, kombinasi kontrak jangka panjang dan spot untuk stabilkan harga | Sales Operation Section Head | 2026-04-24 | 10% | Progress | |
| Risk | FU-0076RR-0128 | 1. Training high risk control protocol (HRCP) terkait dumping high risk 2. Pengadaan simper khusus untuk aktivitas high risk 3. Pemilahan dan pengalokasian operator senior bekerja di aktivitas high risk 4. Dumping limiter (sisi sebelah kanan dan kiri) sebagai pedoman dumping unit 5. Dumpman / spotter sebagai pengarah dumpingan 6. Pondok dumpman sebagai pelindung dumpman dan terdapat pengawasan melekat 7. Penngunaan tool distance meter untuk penentuan dumping limiter 8. Pengawasan melekat di area high risk aktivitas 9. Tower lamp untuk shift II dengan intnesitas minimal 50 lux diarea dumping point | Health, Safety & Environment Department Head | 2026-04-27 | 10% | Open | |
| Risk | FU-0076-2RR-0128 | 1. Training high risk control protocol (HRCP) terkait dumping high risk 2. Pengadaan simper khusus untuk aktivitas high risk 3. Pemilahan dan pengalokasian operator senior bekerja di aktivitas high risk 4. Dumping limiter (sisi sebelah kanan dan kiri) sebagai pedoman dumping unit 5. Dumpman / spotter sebagai pengarah dumpingan 6. Pondok dumpman sebagai pelindung dumpman dan terdapat pengawasan melekat 7. Penngunaan tool distance meter untuk penentuan dumping limiter 8. Pengawasan melekat di area high risk aktivitas 9. Tower lamp untuk shift II dengan intnesitas minimal 50 lux diarea dumping point | Health, Safety & Environment Department Head | 2026-04-27 | 10% | Open | |
| Risk | FU-0171RR-0223 | Benchmark remunerasi, penguatan hubungan industrial dan program retensi talenta kunci | HC Operations & General Affairs Section Head | 2026-05-04 | 10% | Progress | |
| Risk | FU-0012RR-0012 | Eksplorasi berkelanjutan, akuisisi konsesi baru | Sr Business Development Specialist | 2026-05-05 | 10% | Progress | |
| Risk | FU-0071RR-0123 | Pengendalian sarang tawon dilakukan dengan mengunakan Safety khusus Tawon | Reclamation, Post Mining, & Quality Management System Department Head | 2026-05-05 | 100% | Closed | |
| Risk | FU-0181RR-0233 | Monitoring pergerakan tanah (prisma/radar) pada lereng dan area infrastruktur | Engineering Section Head | 2026-05-05 | 10% | Progress | |
| Risk | FU-0106RR-0158 | Melakukaan weekly meeting update progress project Pengalihan Jalan Hauling Koridor 1 Blok 3 untuk memastikan progress pada di setiap lini departemen | Civil Engineering & Infrastructure Section Head | 2026-05-06 | 100% | Closed | |
| Risk | FU-0106-2RR-0158 | Proses pembebasan lahan area Pengalihan Jalan Hauling Koridor 1 sudah mulai terprogress dan sudah ada area lahan bebas pada tanggal 15 April 2026 | Civil Engineering & Infrastructure Section Head | 2026-05-06 | 100% | Closed | |
| Risk | FU-0106-3RR-0158 | Proses tender pemilihan kontraktor konstruksi harus selesai maksimal pada 6 April 2026 | Civil Engineering & Infrastructure Section Head | 2026-05-06 | 100% | Closed | |
| Risk | FU-0164RR-0216 | Integrasi risiko iklim (climate risk) ke dalam enterprise risk register dan pelaporan Dewan | Risk Management Section Head | 2026-05-06 | 10% | Progress | |
| Risk | FU-0035RR-0035 | Segregasi stockpile | Reclamation, Post Mining, & QMS Department Head | 2026-05-13 | 100% | Closed | |
| Risk | FU-0116RR-0168 | Sudah dilakukan followup dengan tim OSTS dengan merencanakan pekerjaan docking serta koordinasi dengan pihak KSOP | Transhipment Section Head | 2026-05-13 | 10% | Progress | |
| Risk | FU-0176RR-0228 | Patroli terpadu dengan aparat, pemasangan CCTV & portal, serta program alternatif mata pencaharian warga | CSR/Community Development Section Head | 2026-05-13 | 10% | Progress | |
| Risk | FU-0015RR-0015 | ESG management, CSR, komunikasi publik yang baik | Sr Business Development Specialist | 2026-05-14 | 100% | Closed | |
| Risk | FU-0127RR-0179 | Pembentukan tim satgas karhutla bersama masyarakat, penyediaan water tank & pompa portable, patroli titik api harian berbasis data hotspot BMKG/LAPAN | Environment Section Head | 2026-05-14 | 10% | Progress | |
| Risk | FU-0049RR-0101 | Mendengarkan keluhan dan kepentingan pemerintah desa dan juga menyampaikan kondisi dan keterbatasan perusahaan | Government Relation & Legal Section Head | 2026-05-18 | 10% | Open | |
| Risk | FU-0049-2RR-0101 | Meningkatkan intensitas komunikasi baik formal maupun informal dengan seluruh pemerintah desa di wilayah operasional perusahaan | Government Relation & Legal Section Head | 2026-05-18 | 10% | Open | |
| Risk | FU-0089RR-0141 | - Follow up pembebasan lahan ke tim LA terkait pembebasan lahan di area blok 3 utara - Akan dibebaskan lahan an Pak Hardi dan Pak Iqbal | Short Term Mine Planning Section Head | 2026-05-18 | 100% | Closed | |
| Risk | FU-0086RR-0138 | Dilakukan reforecast dan rescheduling sekuen penambangan di pit warutas bersama kontraktor PT MAJU | Short Term Mine Planning Section Head | 2026-05-20 | 10% | Progress | |
| Risk | FU-0157RR-0209 | Fuel management system & pengawasan losses pengisian unit kontraktor | Procurement Section Head | 2026-05-21 | 10% | Progress | |
| Risk | FU-0038RR-0038 | Environmental management system | Government Relation Section Head | 2026-05-22 | 10% | Continue | |
| Risk | FU-0001RR-0001 | Pemasangan slope monitoring radar & redesain geometri lereng | Production Section Head | 2026-05-25 | 10% | Progress | |
| Risk | FU-0128RR-0180 | Pembuatan sekat bakar (fire break) di batas area reklamasi, penyediaan APAR & fire truck standby, sosialisasi larangan land clearing dengan api | Health, Safety & Environment Department Head | 2026-05-25 | 10% | Progress | |
| Risk | FU-0074RR-0126 | Melakukan analisa dan kajian kembali terkait catchment area yang masuk ke SP serta treatmen yang harus dilakukan | Health, Safety & Environment Department Head | 2026-05-26 | 10% | Progress | |
| Risk | FU-0104RR-0156 | Update FS (Feasibility study) yang mencakup area pengalihan Jalan Aspal Section 1 Pit B Blok II | Civil Engineering & Infrastructure Section Head | 2026-05-26 | 10% | Open | |
| Risk | FU-0052RR-0104 | Penyediaan back up jaringan sehingga dapat mengcover kondisi putus jaringan | Port Operation Section Head | 2026-05-27 | 100% | Closed | |
| Risk | FU-0047RR-0047 | ESG monitoring | CSR/Community Development Section Head | 2026-05-28 | 100% | Closed | |
| Risk | FU-0028RR-0028 | Due diligence kontraktor | Engineering Section Head | 2026-05-29 | 10% | Progress | |
| Risk | FU-0150RR-0202 | Penetapan batas cuaca operasi (weather limit), monitoring prakiraan BMKG dan protokol evakuasi crew | Transhipment Section Head | 2026-05-29 | 10% | Progress | |
| Risk | FU-0006RR-0006 | Implementasi cyber insurance & penguatan IT general controls | IT Department Head | 2026-06-03 | 10% | Progress | |
| Risk | FU-0062RR-0114 | Repair sambungan belt BLC metode cold | Plant & Maintenance Section Head | 2026-06-08 | 10% | Open | |
| Risk | FU-0062-2RR-0114 | Repair sambungan Belt conveor BLC | Plant & Maintenance Section Head | 2026-06-08 | 100% | Closed | |
| Risk | FU-0080RR-0132 | membuat standar parameter untuk mengatur proses penimbangan batubara di stockpile, termasuk untuk batu lengket atau muatan sisa | CPP & Road Maintenance Section Head | 2026-06-08 | 100% | Closed | |
| Risk | FU-0145RR-0197 | Monitoring kualitas udara ambien di titik pemukiman & pelaporan berkala ke instansi lingkungan | Health, Safety & Environment Department Head | 2026-06-08 | 10% | Progress | |
| Risk | FU-0025RR-0025 | Defensive driving dan fatigue management | Plant & Maintenance Section Head | 2026-06-09 | 10% | Open | |
| Risk | FU-0111RR-0163 | berkoordinasi dengan Commser terkait history komplain area Desa X | Government Relation Section Head | 2026-06-09 | 10% | Progress | |
| Risk | FU-0111-2RR-0163 | berkoordinasi dengan CSR terkait rencana pemberdayaan masyarakat /program UMKM khususnya wilayah Desa X yang akan berjalan pada 20226 | Government Relation Section Head | 2026-06-09 | 10% | Progress | |
| Risk | FU-0111-3RR-0163 | melakukan koordinasi dengan enviro terkait pembahasan test limbah yang masuk lahan warga & rencana perbaikan lingkungan oleh AGM | Government Relation Section Head | 2026-06-09 | 10% | Open | |
| Risk | FU-0111-4RR-0163 | melakukan pendekatan dengan Kades & tokoh masyarakat desa X | Government Relation Section Head | 2026-06-09 | 10% | Open | |
| Risk | FU-0111-5RR-0163 | melakukan pertemuan dengan kades X sekaligus halal bihalal selepas hari raya idulfitri, Kades X menyampaikan tindak lanjut isu lingkungan pada area desa X | Government Relation Section Head | 2026-06-09 | 100% | Closed | |
| Risk | FU-0124RR-0176 | 1. Membuat Tools Monitoring Untuk Mengetahui Re Order Point Qty 2. Penyesuaian MOQ, Leadtime Pembelian sesuai Aktual dan disepakati bersama 3. Sharing Pembagian Penjadwalan meeting | Warehouse & Logistic Section Head | 2026-06-09 | 10% | Open | |
| Risk | FU-0124-2RR-0176 | Perhitungan Min Max telah di Sesuaikan dengan Leadtime Pembelian sehingga di mitigas | Warehouse & Logistic Section Head | 2026-06-09 | 100% | Closed | |
| Risk | FU-0155RR-0207 | Penyesuaian strip ratio dan mine plan agar cost per ton tetap kompetitif saat harga rendah | Long Term & Strategic Plan Section Head | 2026-06-09 | 10% | Progress | |
| Risk | FU-0077RR-0129 | Melakukan perbaikan terkait area CP5 IDM dengan membuat paritan aliran air | CPP & Road Maintenance Section Head | 2026-06-10 | 10% | Progress | |
| Risk | FU-0166RR-0218 | Peningkatan safety stock critical part, kualifikasi vendor alternatif lokal dan kontrak konsinyasi | Warehouse & Logistic Section Head | 2026-06-11 | 10% | Progress | |
| Risk | FU-0135RR-0187 | Perencanaan draft survey harian, penggunaan tongkang kapasitas lebih kecil saat air rendah, dan penambahan window pelayaran malam | Transhipment Section Head | 2026-06-15 | 10% | Progress | |
| Risk | FU-0059RR-0111 | Mempercepat proses recovery perangkat (reduce downtime) dengan cara quick replacement perangkat dan melakukan Backup otomatis harian/mingguan sehingga pada saat terjadi insiden langsung dilakukan quick action dengan replace perangkat dan restore configurasi | IT Department Head | 2026-06-17 | 10% | Progress | |
| Risk | FU-0138RR-0190 | Optimasi ritase hauling untuk menyesuaikan kapasitas stock ROM saat pengapalan tertunda | Hauling Section Head | 2026-06-17 | 10% | Progress | |
| Risk | FU-0121RR-0173 | telah dilakukan progress pengalihan jalan KCM sudah close per tanggal 07 - 04 -2026 sehingga menurunkan resiko longsor jalan hauling KCM. paralel dengan pembuatan kajian geoteknik lowwall panel 40 Pit HRS | Mining Production Section Head | 2026-06-18 | 10% | Progress | |
| Risk | FU-0173RR-0225 | Perencanaan tenaga kerja lokal (local content) dan pemenuhan kewajiban BPJS seluruh pekerja termasuk THL | HCGA Section Head | 2026-06-18 | 10% | Progress | |
| Risk | FU-0182RR-0234 | Natural hedging pendapatan USD, penjadwalan ulang pinjaman dan monitoring eksposur kurs bulanan | Finance AP & Banking Section Head | 2026-06-19 | 10% | Progress | |
| Risk | FU-0018RR-0018 | Geoteknik monitoring, radar slope stability | Production Section Head | 2026-06-22 | 10% | Continue | |
| Risk | FU-0165RR-0217 | Percepatan program reklamasi & carbon sink sebagai bukti komitmen dekarbonisasi | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-22 | 10% | Progress | |
| Risk | FU-0032RR-0032 | Scheduling dan buffer stock | Port Operation Section Head | 2026-06-26 | 10% | Progress | |
| Risk | FU-0117RR-0169 | Proses pengajuan perpanjangan Surat Laut ke KSOP oleh Dept. Marine di bantu Dept. CCI dari tahun 2021 sd sekarang mengunakan Perijinan dari Dinas Perhubungan Kal Sel | Transhipment Section Head | 2026-06-26 | 100% | Closed | |
| Risk | FU-0085RR-0137 | Dilakukan kajian back analisa oleh tim geoteknik AGM untuk memberikan rekomendasi geometri lereng yang aman | Short Term Mine Planning Section Head | 2026-06-29 | 10% | Progress | |
| Risk | FU-0126RR-0178 | 1. Pergantian Metode Sampling 2. Pergantian Micron Filter dari 10 Micron ke 6 Micron | Warehouse & Logistic Section Head | 2026-06-29 | 10% | Open | |
| Risk | FU-0126-2RR-0178 | Membuat Tools Flushing dan Pembuatan Jadwal Flushing Secara Berkala Per Bulan sehingga menurunkan periode pergantian Filter Fuel Modul | Warehouse & Logistic Section Head | 2026-06-29 | 10% | Open | |
| Risk | FU-0126-3RR-0178 | Pergantian Filter 6 Micron | Warehouse & Logistic Section Head | 2026-06-29 | 100% | Closed | |
| Risk | FU-0126-4RR-0178 | Pergantian Jenis Bottle Sample | Warehouse & Logistic Section Head | 2026-06-29 | 100% | Closed | |
| Risk | FU-0170RR-0222 | Audit keamanan informasi tahunan dan pengujian rencana pemulihan bencana (DRP) | Risk Management Section Head | 2026-06-29 | 10% | Progress | |
| Audit | AF-2025-049 | Evaluasi pengendalian: Kecemburuan sosial antar desa | Government Relation & Legal Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-050 | Evaluasi pengendalian: Limpasan air ke lahan belum bebas milik warga yang disebabkan sedimentasi di jalur paritan | Government Relation & Legal Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-051 | Evaluasi pengendalian: Lahan Hidayat Bara 4 belum dapat dikerjakan | Government Relation & Legal Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-052 | Evaluasi pengendalian: Jaringan internet dan server down menyebabkan terhambatnya proses penimbangan DT Coal Hauling | Port Operation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-053 | Evaluasi pengendalian: Harga solar industri B40 acuan pertamina menembus diatas Rp. 30.000 per liter, disebabkan oleh lonja | Port Operation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-054 | Evaluasi pengendalian: Debu batubara dari ROM BSSR | Port Operation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-055 | Evaluasi pengendalian: Produtivity Barging Waktu Loading Barging 7,500 MT melebihi 7.5 jam | Port Operation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-056 | Evaluasi pengendalian: JKK & JKM Tenaga Harian Lepas (THL) belum terdaftar | HCGA Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-057 | Evaluasi pengendalian: Galian Pada Pekerjaan Pembuatan Pintu Air SP12 Berisiko Terjadi Longsor dan Patah Outlet Pintu Air | Engineering Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-058 | Evaluasi pengendalian: 'Pinalti royalti dari vendor resmi applikasi (license) | IT Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-059 | Evaluasi pengendalian: Kerusakan perangkat jaringan (hardware failure,Bad sector, Mati total) menyebabkan hilangnya akses t | IT Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-060 | Evaluasi pengendalian: Dengan adanya penambahan produksi BSSR menjadi 7,3 juta ton, maka perlu dipersiapkan infrastruktur k | Production Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-061 | Evaluasi pengendalian: Kontaminasi Batubara dari pit bara 6,7 dan 8 | Production Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-062 | Evaluasi pengendalian: Sambungan belt conveyor BLC putus (LC05001) | Plant & Maintenance Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-063 | Evaluasi pengendalian: TRACK LINK PUTUS (DZ05001) | Plant & Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-064 | Evaluasi pengendalian: Tyre pos 1 atau pos 2 bocor/meledak (Blownout) WL05002 | Plant & Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-065 | Evaluasi pengendalian: BD Unschedule Tyre pos 1 BlownOut (meledak) WL05001 CAT 980NG | Plant & Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-066 | Evaluasi pengendalian: Bearing head feeder failure (shaft worn out) | Plant & Maintenance Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-067 | Evaluasi pengendalian: Area Bara 678 berada pada wilayah Ring 3 IKN yang memiliki ketentuan tata ruang khusus sesuai RTRW I | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-068 | Evaluasi pengendalian: Terdapat potensi tanaman kerdil (tidak tumbuh sesuai dengan target yang seharusnya) di BARA 1,2,3 | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-069 | Evaluasi pengendalian: Pada area Bara 1,2 3, 4, 5,6,7,8 rencana dan realisasi bukaan lahan berdasarkan dokumen Rencana rekl | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-070 | Evaluasi pengendalian: Terdapat patahan area bank Soil dan reklamasi bara 7 yang berpotensi menggangu lahan reklamasi dan l | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-071 | Evaluasi pengendalian: Terdapat sarang tawon pada area perawatan reklamasi opd 5 | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-072 | Evaluasi pengendalian: Terjadinya musim kemarau yang berdampak pada penanaman. | Reclamation, Post Mining, & Quality Management System Department Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-073 | Evaluasi pengendalian: Terjadi kesalahan order barang, terdapat perbedaan barang yang di beli dan yang dibutuhkan user | Procurement Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-074 | Evaluasi pengendalian: SP 1 di port kompartemen 2 belum terbentuk maksimal | Health, Safety & Environment Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-075 | Evaluasi pengendalian: settling pond area bara 8 belum terbentuk dan belum berizin | Health, Safety & Environment Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-076 | Evaluasi pengendalian: Potensi terjadi case fatality / LTI karena aktivitas dumping highrisk mengarah air disposal IPD BARA | Health, Safety & Environment Department Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-077 | Evaluasi pengendalian: banjir di area cp 05 idm 3, berpotensi merendam perangkat electric & genset | CPP & Road Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-078 | Evaluasi pengendalian: Intensitas dan frekwensi hujan tinggi di area PIT Blok 4 | CPP & Road Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-079 | Evaluasi pengendalian: Muatan sisa batubara lengket di vessel dump truck kontraktor hauling yang tidak dikembalikan baik di | CPP & Road Maintenance Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-080 | Evaluasi pengendalian: aktivitas penimbangan batu bara di area stock pile | CPP & Road Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-081 | Evaluasi pengendalian: Permintaan Rental WT 20 KL rekomendasi pejabat desa Suato Tatakan dengan kondisi unit tahun 2013 den | CPP & Road Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-082 | Evaluasi pengendalian: Harga fuel yang terus naik sejak bulan Maret 2026 berpotensi menurunnya UA (Utility Availability) Du | CPP & Road Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-083 | Evaluasi pengendalian: Komplain lahan warga Desa Kembang Habang Baru yang lahan kebun karetnya terganggu kegiatan operasion | CSR/Community Development Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-084 | Evaluasi pengendalian: Kasus Limbah Sungai Bahalang (Masyarakat meminta untuk dilakukan pembebasan lahan disekitar kanal ka | CSR/Community Development Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-085 | Evaluasi pengendalian: Terjadi potensi failure di area low wall pit tengah Blok 4 dikarenakan: Material: Terdapat material | Short Term Mine Planning Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-086 | Evaluasi pengendalian: Tidak adanya kegiatan mud handling di area blok 3 warutas dikarenakan: Man: PT MAJU sebagai kontrakt | Short Term Mine Planning Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-087 | Evaluasi pengendalian: Tidak tercapainya rencana produksi 2026 Blok 4 sebanyak 6,2 Juta ton pada EoY 2026 dikarenakan: Mach | Short Term Mine Planning Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-088 | Evaluasi pengendalian: Tertundanya perizinan settling pond all area pada pengajuan pertek AGM 2026 dikarenakan : Man: Konsu | Short Term Mine Planning Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-089 | Evaluasi pengendalian: Pembebasan lahan dengan total luasan 16.84 Ha terhambat di area pit dan disposal blok 3N sesuai plan | Short Term Mine Planning Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-090 | Evaluasi pengendalian: Terlambatnya finalisasi pit D blok 2 panel 35-43 untuk rencana IPD bulan September 2026 dengan volum | Short Term Mine Planning Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-091 | Evaluasi pengendalian: Terlambatnya finalisasi Pit Tengah Blok 4 panel 37 yang direncanakan selesai pada Bulan Mei 2026 dik | Short Term Mine Planning Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-092 | Evaluasi pengendalian: Keterlambatan finalisasi pit warute area sidewall Api-api s.d. RL-80 yang direncanakan selesai pada | Short Term Mine Planning Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-093 | Evaluasi pengendalian: Tidak bebasnya rencana pembebasan lahan OPD 2 seluas 14,18 Ha yang akan direncanakan digunakan sebag | Short Term Mine Planning Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-094 | Evaluasi pengendalian: Potensi terjadinya kesalahan pada saat proses pembayaran tagihan supplier dikarenakan human error sa | Finance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-095 | Evaluasi pengendalian: Potensi terjadinya keterlambatan pembayaran (overdue) dari tanggal pembayaran yang sudah di sepakati | Finance Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-096 | Evaluasi pengendalian: Potensi terjadi keterlambatan pembayaran (overdue) dari tanggal yang sudah di sepakati antara pihak | Finance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-097 | Evaluasi pengendalian: 1. Risiko SDM tidak terkontrol Potensi konflik karyawan, turnover tinggi, atau masalah budaya kerja | HC Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-098 | Evaluasi pengendalian: TInggi nya tingkat kecelakaan di mining dan hauling periode triwulan 1 di PT AGM | Safety & Health Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-099 | Evaluasi pengendalian: Pemenuhan Legal Complience tercapai 100% | Safety & Health Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-100 | Evaluasi pengendalian: Kegiatan STL tidak tercapai bulan Januari-Maret 2026, menyebabkan penanaman area reklamasi tidak ter | Safety & Health Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-101 | Evaluasi pengendalian: Tidak tersedianya klinik dan paramedis yang dedicated di mess untuk karyawan AGM | Safety & Health Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-102 | Evaluasi pengendalian: Tidak adanya perhitungan pemakaian solar di Mega Injeksi AGM | Safety & Health Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-103 | Evaluasi pengendalian: Kurangnya Partisipasi dari masing-masing Department dan terbatasnya frekuensi dan durasi pelatihan | Safety & Health Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-104 | Evaluasi pengendalian: Konstruksi Pengalihan Jalan Aspal Kabupaten PIT B Blok 2 tidak bisa dimulai pada Desember 2026 yang | Civil Engineering & Infrastructure Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-105 | Evaluasi pengendalian: Konstruksi Pengalihan Jalan Aspal Kabupaten PIT B Blok 2 tidak selesai pada November 2026 yang diseb | Civil Engineering & Infrastructure Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-106 | Evaluasi pengendalian: Konstruksi Pengalihan Jalan Hauling Koridor 1 Blok 3 tidak selesai pada Juni 2026 yang disebabkan ol | Civil Engineering & Infrastructure Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-107 | Evaluasi pengendalian: Terjadinya Cut Fiber Optik yang menyebabkan putusnya jaringan(koneksi internet ataupun cctv) | IT Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-108 | Evaluasi pengendalian: Software Unlicense | IT Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-109 | Evaluasi pengendalian: Server DOWN akibat sambaran petir | IT Department Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-110 | Evaluasi pengendalian: Network DOWN | IT Department Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-111 | Evaluasi pengendalian: potensi pembatalan pembebasan lahan oleh pemilik lahan pada area blok 4 utara dikarenakan terhambatn | Government Relation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-112 | Evaluasi pengendalian: Izin perpanjangan crossing 6 Ruas di kab.tapin yang akan habis pada 2 Maret 2026 | Government Relation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-113 | Evaluasi pengendalian: waktu proses pembayaran lahan memakan waktu lama dikarenakan tidak ada acuan target proses pembayara | Government Relation Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-114 | Evaluasi pengendalian: Tahun 2018 : ada complain dari Petani terkait Hutan Karet yang terkena dampak tambang (Hutan Lindung | Government Relation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-115 | Evaluasi pengendalian: Proses pembebasan lahan blok 4 desa suato tatakan | Government Relation Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-116 | Evaluasi pengendalian: Perijinan Surat Laut dari KSOP untuk TB. Ari 1 sd 8 dan Tk. Apri 1 sd 12 saat ini sudah dilakukan en | Transhipment Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-117 | Evaluasi pengendalian: Perijinan Surat Laut dari KSOP untuk Tug Boat & Tongkang diberlakukan tahun 2026 Perijinan dari Dina | Transhipment Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-118 | Evaluasi pengendalian: Regulasi untuk penggunaan fuel dengan Biodiesel B40 dan Tahun 2026 menuju B50 | Plant & Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-119 | Evaluasi pengendalian: Unit Wheel Loader WL06025 & WL06026 Pin Bucket & Hole Pin Mengalami Kerusakan Berulang | Plant & Maintenance Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-120 | Evaluasi pengendalian: PA Unit mining kontraktor HRS dibawah target | Mining Production Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-121 | Evaluasi pengendalian: Longsor nya jalan hauling KCM km 3 di blok 4 | Mining Production Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-122 | Evaluasi pengendalian: belum ada update RAB menyesuaikan kenaikan harga solar, sehingga progress Tender mundur | Warehouse & Logistic Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-123 | Evaluasi pengendalian: Kelangkaan solar disebabkan oleh berkurangnya ketersediaan stok dalam negeri sebagai dampak dari kon | Warehouse & Logistic Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-124 | Evaluasi pengendalian: Target Service Level 100% Per Bulan terdapat Beberapa Resiko : Man : Inventory Terlambat Reffil Item | Warehouse & Logistic Section Head | 2026-06-30 | 60% | In Progress | |
| Audit | AF-2025-125 | Evaluasi pengendalian: Beberapa Kebutuhan Sparepart A2B Caterpillar terkendala Larangan Terbatas (Lartas) | Warehouse & Logistic Section Head | 2026-06-30 | 10% | Open | |
| Audit | AF-2025-126 | Evaluasi pengendalian: Target Fuel Accuracy 99.5% - Perubahan Jenis Solar B40 ke B50 Pada Bulan Juni 2026 1. Material : men | Warehouse & Logistic Section Head | 2026-06-30 | 60% | In Progress | |
| Risk | FU-0013RR-0013 | Diversifikasi pelanggan dan negara tujuan ekspor | Sr Business Development Specialist | 2026-07-01 | 10% | Open | |
| Risk | FU-0160RR-0212 | Simulasi dampak tarif royalti & DHE terhadap kewajiban perpajakan dan penyesuaian perencanaan pajak | Tax Department Head | 2026-07-01 | 10% | Progress | |
| Risk | FU-0094RR-0146 | Opsi 1 : Melakukan negosisasi dengan pihak yang menerima dana untuk dapat mengembalikan dana tersebut sehingga dana dapat masuk kembali ke rekening perusahaan Opsi 2 : Jika Opsi 1 tidak berhasil maka user yang bersangkutan melakukan penggantian dana tersebut sebagai bentuk tanggung jawab atas kesalahan yang dilakukan | Finance Section Head | 2026-07-02 | 100% | Closed | |
| Risk | FU-0156RR-0208 | Kontrak pasokan fuel multi-vendor, penambahan kapasitas storage tank dan monitoring stok harian | Warehouse & Logistic Section Head | 2026-07-06 | 10% | Progress | |
| Risk | FU-0039RR-0039 | Monitoring kewajiban PNBP | Government Relation Section Head | 2026-07-07 | 100% | Closed | |
| Risk | FU-0099RR-0151 | - Koordinasi / Meeting Mingguan dengan Departmen Terkait - Monitoring Legal Compliance based on Deptarment | Safety & Health Section Head | 2026-07-09 | 10% | Progress | |
| Risk | FU-0129RR-0181 | Penyiraman berkala area revegetasi rawan kering & penanaman jenis tanaman tahan api pada zona perimeter | Reclamation Section Head | 2026-07-09 | 10% | Progress | |
| Risk | FU-0016RR-0016 | Good Corporate Governance (GCG) | Sr Business Development Specialist | 2026-07-10 | 10% | Progress | |
| Risk | FU-0053RR-0105 | Komersial - Sharing terkait pembelian fuel ke vendor paling murah dan didapat stock Operasional - Optimasi Cycle Time - Fuel management system (Monitoring Stock Fuel Kontraktor) Strategis - Setting fleet sesuai plan barging | Port Operation Section Head | 2026-07-10 | 100% | Closed | |
| Risk | FU-0075RR-0127 | Melakukan perubahan skema dewatering khususnya untuk area catchment SP11 (jangan sampai membuang air tanpa melewati SP) | Health, Safety & Environment Department Head | 2026-07-10 | 10% | Open | |
| Risk | FU-0075-2RR-0127 | Untuk PERTEK tetap dilanjutkan, namun untuk SLO akan dilakukan analisa kembali | Health, Safety & Environment Department Head | 2026-07-10 | 10% | Progress | |
| Risk | FU-0046RR-0046 | Reklamasi progresif | CSR/Community Development Section Head | 2026-07-14 | 10% | Continue | |
| Risk | FU-0005RR-0005 | Optimalisasi settling pond & pemantauan kualitas air rutin | Health, Safety & Environment Department Head | 2026-07-17 | 10% | Progress | |
| Risk | FU-0056RR-0108 | Mengajukan registrasi akun SIPP ke BPJS Ketenagakerjaan | HCGA Section Head | 2026-07-21 | 100% | Closed | |
| Risk | FU-0065RR-0117 | Plan replace tyre di next service 250h estimasi tgl 26 Feb 2026 | Plant & Maintenance Section Head | 2026-07-22 | 100% | Closed | |
| Risk | FU-0024RR-0024 | Safety stock dan kontrak supplier | Plant & Maintenance Section Head | 2026-07-23 | 10% | Progress | |
| Risk | FU-0043RR-0043 | Credit assessment buyer | Finance AP & Banking Section Head | 2026-07-23 | 100% | Closed | |
| Risk | FU-0079RR-0131 | Sosialisasi prosedur pengembalian muatan sisa lengket di vessel ke driver kontraktor hauling dan operator timbangan, yaitu Driver Dump Truck WAJIB kembali ke port tujuan untuk mengembalikan sisa muatan apabila melanggar akan dikenakan sanksi Pencabutan kimper/grounded. | CPP & Road Maintenance Section Head | 2026-07-23 | 100% | Closed | |
| Risk | FU-0079-2RR-0131 | Sosialisasi prosedur pengembalian muatan sisa lengket di vessel ke driver kontraktor hauling dan operator timbangan, yaitu Driver Dump Truck WAJIB kembali ke port tujuan untuk mengembalikan sisa muatan apabila melanggar akan dikenakan sanksi Pencabutan kimper/grounded. | CPP & Road Maintenance Section Head | 2026-07-23 | 10% | Open | |
| Risk | FU-0112RR-0164 | Komunikasi dengan tim CHRM untuk antisipasi kondisi tersebut | Government Relation Section Head | 2026-07-23 | 100% | Closed | |
| Risk | FU-0112-2RR-0164 | Komunikasi dgn dinas terkait untuk percepatan izin terbit | Government Relation Section Head | 2026-07-23 | 10% | Open | |
| Risk | FU-0112-3RR-0164 | Melakukan perpanjangan ijin crossing | Government Relation Section Head | 2026-07-23 | 100% | Closed | |
| Risk | FU-0144RR-0196 | Program kesehatan masyarakat (pemeriksaan ISPA gratis) dan forum komunikasi warga terdampak debu | CSR/Community Development Section Head | 2026-07-23 | 10% | Progress | |
| Risk | FU-0123RR-0175 | 1. Analisa MOPS (Mean of Plats Singapore) atas oil price, Analisa kurs USD, harga dasar edaran pertamina, Brent Crude Oil. sbg Early warning kenaikan harga dan potensi gangguan supply 2. Menerapkan non single supplier (baik dari distributir pertamina maupun non distributor non pertamina), bertujuan menghindari ketergantungan pada satu pemasok 3. Negosiasi forecast kebutuhan per periode, agar vendor dapat mengalokasikan kuota lebih awal 4. Maximize stock fuel di storage, untuk menjamin operasional saat terjadi kelangkaan sementara | Warehouse & Logistic Section Head | 2026-07-24 | 100% | Closed | |
| Risk | FU-0123-2RR-0175 | 1. Analisa; MOPS (Mean of Plats Singapore) atas oil price, kurs USD, harga dasar edaran pertamina, Brent Crude Oil 2. Menerapkan non single supplier (baik dari pertamina maupun non pertamina) 3. Negosiasi forecast kebutuhan per periode 4. Maximize stock fuel sebelum harga naik | Warehouse & Logistic Section Head | 2026-07-24 | 10% | Open | |
| Risk | FU-0154RR-0206 | Pengendalian biaya operasional site dan monitoring cost per ton bulanan | Finance Section Head | 2026-07-24 | 10% | Progress | |
| Risk | FU-0096RR-0148 | - Memperbaiki proses penyusunan dokumen (kelengkapan tagihan) dan hal-hal lain yang berkaitan dengan tagihan tersebut seperti permintaan approval - Memisahkan skala prioritas antara tagihan prioritas (yang TOPnya < 7 hari) dengan tagihan normal(yang TOPnya >30 hari) | Finance Section Head | 2026-07-27 | 10% | Open | |
| Risk | FU-0132RR-0184 | Penyesuaian jadwal transhipment saat kabut asap, koordinasi dengan syahbandar & penggunaan radar/AIS | Transhipment Section Head | 2026-07-30 | 10% | Progress | |
| Risk | FU-0058RR-0110 | Melakukan control dengan membuat login local dan login administrator di semua pc/laptop user sehingga user tidak bisa melakukan instal sembarangan tanpa persetujuan administrator | IT Department Head | 2026-07-31 | 100% | Closed | |
| Risk | FU-0058-2RR-0110 | mendaftarkan semua list software license sehingga tidak terjadi keterlambatan saat melakukan renewal tahunan | IT Department Head | 2026-07-31 | 100% | Closed | |
| Risk | FU-0021RR-0021 | Infill drilling dan model geologi berkala | Production Section Head | 2026-08-03 | 10% | Open | |
| Risk | FU-0141RR-0193 | Recycling air settling pond untuk kebutuhan penyiraman dan monitoring debit sumber air | Environment Section Head | 2026-08-03 | 10% | Progress | |
| Risk | FU-0120RR-0172 | Membuat kapasitas rencana kerja produksi melebihi target produksi dengan PT. HRS . | Mining Production Section Head | 2026-08-04 | 100% | Closed | |
| Risk | FU-0172RR-0224 | Program pelatihan operator lokal & kerja sama dengan SMK/politeknik daerah | HC Section Head | 2026-08-04 | 10% | Progress | |
| Risk | FU-0183RR-0235 | Pengendalian pembelian berbasis USD dan review kontrak berdenominasi asing | Finance Section Head | 2026-08-04 | 10% | Progress | |
| Risk | FU-0019RR-0019 | Dewatering system, pompa cadangan | Production Section Head | 2026-08-05 | 100% | Closed | |
| Risk | FU-0167RR-0219 | Perpanjangan lead time planning & pemantauan status pengiriman part impor | Procurement Section Head | 2026-08-06 | 10% | Progress | |
| Risk | FU-0033RR-0033 | Weather monitoring system | Port Operation Section Head | 2026-08-12 | 10% | Open | |
| Risk | FU-0048RR-0048 | ESG roadmap | CSR/Community Development Section Head | 2026-08-12 | 10% | Progress | |
| Risk | FU-0084RR-0136 | Melakukan pendekatan dengan tokoh masyarakat atau tokoh agama untuk meredam aksi masyarakat | CSR/Community Development Section Head | 2026-08-13 | 100% | Closed | |
| Risk | FU-0169RR-0221 | Implementasi backup 3-2-1, EDR pada seluruh endpoint, simulasi phishing dan security awareness training | IT Department Head | 2026-08-13 | 10% | Progress | |
| Risk | FU-0178RR-0230 | Verifikasi dokumen kepemilikan, mediasi bersama pemerintah daerah dan percepatan pembayaran ganti rugi | Government Relation Section Head | 2026-08-13 | 10% | Progress | |
| Risk | FU-0095RR-0147 | - Memperbaiki serta mempercepat proses penyusunan dokumen (kelengkapan tagihan) dan hal-hal lain yang berkaitan dengan tagihan tersebut seperti permintaan approval tagihan sehingga tagihan selesai tepat pada waktunya - Memisahkan skala prioritas antara tagihan prioritas dengan tagihan normal serta membuat monitoring atas tagihan tersebut sehingga tagihan termonitor dengan baik dan dapat diketahui jika ada tagihan yang sudah mendekati jatuh tempo pembayaran | Finance Section Head | 2026-08-17 | 100% | Closed | |
| Risk | FU-0162RR-0214 | Pemenuhan kewajiban DMO ke PLN/industri domestik dan dokumentasi realisasinya | Sales Operation Section Head | 2026-08-17 | 10% | Progress | |
| Risk | FU-0147RR-0199 | Perbaikan drainase pit, penambahan pompa cadangan dan pengaturan disposal agar tidak menutup aliran air | Production Section Head | 2026-08-20 | 10% | Progress | |
| Risk | FU-0036RR-0036 | SOP sampling dan audit laboratorium | Reclamation, Post Mining, & QMS Department Head | 2026-08-21 | 10% | Progress | |
| Risk | FU-0017RR-0017 | Diversifikasi pasar ekspor dan skenario bisnis | Sr Business Development Specialist | 2026-08-25 | 10% | Open | |
| Risk | FU-0068RR-0120 | Melakukan evaluasi terkait faktor enviro seperti hama penyakit dan evaluasi dalam seleksi bibit | Reclamation, Post Mining, & Quality Management System Department Head | 2026-08-25 | 10% | Open | |
| Risk | FU-0050RR-0102 | Melakukan koordinasi dengan tim Engineering dan Enviro untuk melakukan mapping outer drainage yang mengarah ke lingkungan masyarakat dan action segera | Government Relation & Legal Section Head | 2026-08-26 | 100% | Closed | |
| Risk | FU-0090RR-0142 | - Monitoring PA, UA, dan efektifitas pemompaan yang dilakukan oleh kontraktor PT KPP | Short Term Mine Planning Section Head | 2026-08-26 | 10% | Progress | |
| Risk | FU-0090-2RR-0142 | - Pembuatan staging plan pekerjaan finalisasi pit D panel 35 - 43 bulan Mei - September 2026 | Short Term Mine Planning Section Head | 2026-08-26 | 10% | Progress | |
| Risk | FU-0161RR-0213 | Koordinasi dengan pemerintah daerah dan pusat untuk kepastian pemenuhan kewajiban DMO | Government Relation Section Head | 2026-08-26 | 10% | Progress | |
| Risk | FU-0004RR-0004 | Program CSR kolaboratif & forum musyawarah desa | CSR/Community Development Section Head | 2026-09-01 | 10% | Continue | |
| Risk | FU-0133RR-0185 | Pengaturan jadwal barging dan protokol berhenti muat saat visibilitas rendah di jetty | Port Operation Section Head | 2026-09-02 | 10% | Progress | |
| Risk | FU-0057RR-0109 | Penambahan pancang galam pada titik tanah pembangunan pintu air dan memasang geomembrane agar tanah tidak tergerus air atau rembesan air. Perbaikan akses jalan masuk ke arah pembangunan pintu air untuk memudahkan pengiriman logistik. | Engineering Section Head | 2026-09-03 | 100% | Closed | |
| Risk | FU-0098RR-0150 | Menyusun program dengan seluruh kontraktor untuk menekan angka insiden 2026, membuat sarasehan, dan evaluasi program berjalan | Safety & Health Section Head | 2026-09-03 | 10% | Progress | |
| Risk | FU-0078RR-0130 | Melakukan re-planning carry over volume kebutuhan GAR34 pada hari berikutnya | CPP & Road Maintenance Section Head | 2026-09-07 | 10% | Progress | |
| Risk | FU-0027RR-0027 | KPI contractor dan evaluasi berkala | Engineering Section Head | 2026-09-08 | 100% | Closed | |
| Risk | FU-0045RR-0045 | Community engagement | CSR/Community Development Section Head | 2026-09-08 | 10% | Open | |
| Risk | FU-0113RR-0165 | perlunya standar acuan baku dalam proses pembayaran lahan | Government Relation Section Head | 2026-09-08 | 100% | Closed | |
| Risk | FU-0122RR-0174 | TESTING | Warehouse & Logistic Section Head | 2026-09-08 | 10% | Open | |
| Risk | FU-0097RR-0149 | Melakukan identifikasi risk management diinternal Departemen dan grading priority risk | HC Section Head | 2026-09-10 | 10% | Progress | |
| Risk | FU-0103RR-0155 | - Monitoring Pelaksanaan Training by Dept - Pelaksanaan Training Bulanan Rutin di 3 Area | Safety & Health Section Head | 2026-09-14 | 100% | Closed | |
| Risk | FU-0083RR-0135 | Melakukan tinjauan lapangan dan evaluasi terkait aliran air yang keluar dari AGM | CSR/Community Development Section Head | 2026-09-16 | 10% | Progress | |
| Risk | FU-0140RR-0192 | Penggunaan dust suppressant kimia untuk mengurangi konsumsi air penyiraman jalan | Health, Safety & Environment Department Head | 2026-09-16 | 10% | Progress | |
| Risk | FU-0020RR-0020 | Desain disposal sesuai geoteknik | Production Section Head | 2026-09-17 | 10% | Progress | |
| Risk | FU-0042RR-0042 | Cash flow forecasting | Finance AP & Banking Section Head | 2026-09-17 | 10% | Continue | |
| Risk | FU-0064RR-0116 | Replace tyre pos 1 & 2 | Plant & Maintenance Section Head | 2026-09-17 | 100% | Closed | |
| Risk | FU-0119RR-0171 | - Modifikasi frame boom dan membuat rotable part sehingga jika terjadi kerusakan berulang | Plant & Maintenance Section Head | 2026-09-17 | 10% | Open | |
| Risk | FU-0149RR-0201 | Redesain geometri lereng & kajian geoteknik untuk periode curah hujan tinggi | Engineering Section Head | 2026-09-18 | 10% | Progress | |
| Risk | FU-0184RR-0236 | Percepatan revegetasi area siap tanam, evaluasi bibit tahan kering & pelaporan progres ke ESDM | Reclamation, Post Mining, & Quality Management System Department Head | 2026-09-18 | 10% | Progress | |
| Risk | FU-0030RR-0030 | Road maintenance program | Port Operation Section Head | 2026-09-25 | 10% | Continue | |
| Risk | FU-0061RR-0113 | Telah dilakukan Sosialisasi terkait dengan pengambilan batubara atau coal getting dengan kontraktor MMM | Production Section Head | 2026-09-28 | 10% | Open | |
| Risk | FU-0168RR-0220 | Prioritisasi part kritikal berdasarkan kajian kegagalan unit dan program rebuild komponen | Plant & Maintenance Section Head | 2026-09-28 | 10% | Progress | |
| Risk | FU-0136RR-0188 | Penyesuaian rencana barging dengan data pasang surut, buffer stock di ROM port dan negosiasi ulang jadwal vessel | Port Operation Section Head | 2026-09-29 | 10% | Progress | |
| Audit | AF-2025-127 | Kesiapsiagaan isu eksternal: Kebakaran hutan dan lahan (karhutla) di sekitar wilayah konsesi akibat musim kemarau panja | Environment Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-128 | Kesiapsiagaan isu eksternal: Kebakaran hutan dan lahan (karhutla) di sekitar wilayah konsesi akibat musim kemarau panja | Health, Safety & Environment Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-129 | Kesiapsiagaan isu eksternal: Kebakaran hutan dan lahan (karhutla) di sekitar wilayah konsesi akibat musim kemarau panja | Reclamation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-130 | Kesiapsiagaan isu eksternal: Kebakaran hutan dan lahan (karhutla) di sekitar wilayah konsesi akibat musim kemarau panja | Government Relation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-131 | Kesiapsiagaan isu eksternal: Asap dan penurunan kualitas udara akibat karhutla regional mengganggu visibilitas operasi | Mining Production Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-132 | Kesiapsiagaan isu eksternal: Asap dan penurunan kualitas udara akibat karhutla regional mengganggu visibilitas operasi | Transhipment Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-133 | Kesiapsiagaan isu eksternal: Asap dan penurunan kualitas udara akibat karhutla regional mengganggu visibilitas operasi | Port Operation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-134 | Kesiapsiagaan isu eksternal: Asap dan penurunan kualitas udara akibat karhutla regional mengganggu visibilitas operasi | Safety & Health Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-135 | Kesiapsiagaan isu eksternal: Kemarau panjang akibat El Nino menurunkan tinggi muka air sungai sehingga barging dan tran | Transhipment Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-136 | Kesiapsiagaan isu eksternal: Kemarau panjang akibat El Nino menurunkan tinggi muka air sungai sehingga barging dan tran | Port Operation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-137 | Kesiapsiagaan isu eksternal: Kemarau panjang akibat El Nino menurunkan tinggi muka air sungai sehingga barging dan tran | Sales Operation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-138 | Kesiapsiagaan isu eksternal: Kemarau panjang akibat El Nino menurunkan tinggi muka air sungai sehingga barging dan tran | Hauling Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-139 | Kesiapsiagaan isu eksternal: Kekeringan menyebabkan keterbatasan pasokan air untuk penyiraman jalan, water treatment, d | Civil Engineering & Infrastructure Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-140 | Kesiapsiagaan isu eksternal: Kekeringan menyebabkan keterbatasan pasokan air untuk penyiraman jalan, water treatment, d | Health, Safety & Environment Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-141 | Kesiapsiagaan isu eksternal: Kekeringan menyebabkan keterbatasan pasokan air untuk penyiraman jalan, water treatment, d | Environment Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-142 | Kesiapsiagaan isu eksternal: Kekeringan menyebabkan keterbatasan pasokan air untuk penyiraman jalan, water treatment, d | Reclamation, Post Mining, & Quality Management System Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-143 | Kesiapsiagaan isu eksternal: Debu jalan hauling meningkat drastis pada musim kemarau memicu keluhan masyarakat dan pote | Hauling Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-144 | Kesiapsiagaan isu eksternal: Debu jalan hauling meningkat drastis pada musim kemarau memicu keluhan masyarakat dan pote | CSR/Community Development Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-145 | Kesiapsiagaan isu eksternal: Debu jalan hauling meningkat drastis pada musim kemarau memicu keluhan masyarakat dan pote | Health, Safety & Environment Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-146 | Kesiapsiagaan isu eksternal: Curah hujan ekstrem dan banjir akibat La Nina merendam pit, jalan hauling, dan area infras | Mining Production Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-147 | Kesiapsiagaan isu eksternal: Curah hujan ekstrem dan banjir akibat La Nina merendam pit, jalan hauling, dan area infras | Production Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-148 | Kesiapsiagaan isu eksternal: Curah hujan ekstrem dan banjir akibat La Nina merendam pit, jalan hauling, dan area infras | Civil Engineering & Infrastructure Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-149 | Kesiapsiagaan isu eksternal: Curah hujan ekstrem dan banjir akibat La Nina merendam pit, jalan hauling, dan area infras | Engineering Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-150 | Kesiapsiagaan isu eksternal: Cuaca ekstrem (angin kencang & badai) mengganggu aktivitas transhipment dan keselamatan pe | Transhipment Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-151 | Kesiapsiagaan isu eksternal: Cuaca ekstrem (angin kencang & badai) mengganggu aktivitas transhipment dan keselamatan pe | Port Operation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-152 | Kesiapsiagaan isu eksternal: Fluktuasi harga batubara global (ICI/Newcastle) menurunkan margin dan arus kas perusahaan | Sales Operation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-153 | Kesiapsiagaan isu eksternal: Fluktuasi harga batubara global (ICI/Newcastle) menurunkan margin dan arus kas perusahaan | Finance AP & Banking Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-154 | Kesiapsiagaan isu eksternal: Fluktuasi harga batubara global (ICI/Newcastle) menurunkan margin dan arus kas perusahaan | Finance Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-155 | Kesiapsiagaan isu eksternal: Fluktuasi harga batubara global (ICI/Newcastle) menurunkan margin dan arus kas perusahaan | Long Term & Strategic Plan Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-156 | Kesiapsiagaan isu eksternal: Kenaikan harga BBM industri dan kelangkaan pasokan solar bersubsidi mengganggu operasi ala | Warehouse & Logistic Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-157 | Kesiapsiagaan isu eksternal: Kenaikan harga BBM industri dan kelangkaan pasokan solar bersubsidi mengganggu operasi ala | Procurement Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-158 | Kesiapsiagaan isu eksternal: Kenaikan harga BBM industri dan kelangkaan pasokan solar bersubsidi mengganggu operasi ala | Plant & Maintenance Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-159 | Kesiapsiagaan isu eksternal: Perubahan kebijakan pemerintah (kenaikan tarif royalti, DHE, DMO batubara) meningkatkan be | Government Relation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-160 | Kesiapsiagaan isu eksternal: Perubahan kebijakan pemerintah (kenaikan tarif royalti, DHE, DMO batubara) meningkatkan be | Tax Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-161 | Kesiapsiagaan isu eksternal: Perubahan kebijakan pemerintah (kenaikan tarif royalti, DHE, DMO batubara) meningkatkan be | Government Relation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-162 | Kesiapsiagaan isu eksternal: Perubahan kebijakan pemerintah (kenaikan tarif royalti, DHE, DMO batubara) meningkatkan be | Sales Operation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-163 | Kesiapsiagaan isu eksternal: Tekanan transisi energi global dan pembatasan pembiayaan batubara membatasi akses pendanaa | Finance AP & Banking Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-164 | Kesiapsiagaan isu eksternal: Tekanan transisi energi global dan pembatasan pembiayaan batubara membatasi akses pendanaa | Risk Management Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-165 | Kesiapsiagaan isu eksternal: Tekanan transisi energi global dan pembatasan pembiayaan batubara membatasi akses pendanaa | Reclamation, Post Mining, & Quality Management System Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-166 | Kesiapsiagaan isu eksternal: Ketegangan geopolitik dan gangguan rantai pasok global memperlambat pengadaan spare part i | Warehouse & Logistic Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-167 | Kesiapsiagaan isu eksternal: Ketegangan geopolitik dan gangguan rantai pasok global memperlambat pengadaan spare part i | Procurement Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-168 | Kesiapsiagaan isu eksternal: Ketegangan geopolitik dan gangguan rantai pasok global memperlambat pengadaan spare part i | Plant & Maintenance Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-169 | Kesiapsiagaan isu eksternal: Serangan siber (ransomware/phishing) terhadap sistem ERP dan data operasional perusahaan | IT Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-170 | Kesiapsiagaan isu eksternal: Serangan siber (ransomware/phishing) terhadap sistem ERP dan data operasional perusahaan | Risk Management Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-171 | Kesiapsiagaan isu eksternal: Isu ketenagakerjaan nasional: kenaikan UMP, tuntutan serikat, dan kelangkaan tenaga kerja | HC Operations & General Affairs Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-172 | Kesiapsiagaan isu eksternal: Isu ketenagakerjaan nasional: kenaikan UMP, tuntutan serikat, dan kelangkaan tenaga kerja | HC Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-173 | Kesiapsiagaan isu eksternal: Isu ketenagakerjaan nasional: kenaikan UMP, tuntutan serikat, dan kelangkaan tenaga kerja | HCGA Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-174 | Kesiapsiagaan isu eksternal: Wabah penyakit menular (DBD, ISPA, penyakit endemik) di area site menurunkan produktivitas | Safety & Health Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-175 | Kesiapsiagaan isu eksternal: Wabah penyakit menular (DBD, ISPA, penyakit endemik) di area site menurunkan produktivitas | HCGA Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-176 | Kesiapsiagaan isu eksternal: Aktivitas penambangan tanpa izin (PETI) dan pencurian batubara di area konsesi | CSR/Community Development Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-177 | Kesiapsiagaan isu eksternal: Aktivitas penambangan tanpa izin (PETI) dan pencurian batubara di area konsesi | Land Acquisition & CSR Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-178 | Kesiapsiagaan isu eksternal: Konflik lahan dan tuntutan ganti rugi masyarakat menghambat pembukaan area produksi | Government Relation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-179 | Kesiapsiagaan isu eksternal: Konflik lahan dan tuntutan ganti rugi masyarakat menghambat pembukaan area produksi | Land Acquisition & CSR Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-180 | Kesiapsiagaan isu eksternal: Gempa dan pergerakan tanah akibat perubahan iklim & bencana alam merusak infrastruktur sit | Civil Engineering & Infrastructure Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-181 | Kesiapsiagaan isu eksternal: Gempa dan pergerakan tanah akibat perubahan iklim & bencana alam merusak infrastruktur sit | Engineering Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-182 | Kesiapsiagaan isu eksternal: Kenaikan suku bunga dan pelemahan nilai tukar rupiah meningkatkan beban keuangan | Finance AP & Banking Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-183 | Kesiapsiagaan isu eksternal: Kenaikan suku bunga dan pelemahan nilai tukar rupiah meningkatkan beban keuangan | Finance Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-184 | Kesiapsiagaan isu eksternal: Kegagalan pemenuhan komitmen reklamasi & jaminan reklamasi akibat cuaca ekstrem dan keterb | Reclamation, Post Mining, & Quality Management System Department Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-185 | Kesiapsiagaan isu eksternal: Kegagalan pemenuhan komitmen reklamasi & jaminan reklamasi akibat cuaca ekstrem dan keterb | Reclamation Section Head | 2026-12-31 | 60% | In Progress | |
| Audit | AF-2025-186 | Kesiapsiagaan isu eksternal: Kegagalan pemenuhan komitmen reklamasi & jaminan reklamasi akibat cuaca ekstrem dan keterb | Technical Services Section Head | 2026-12-31 | 60% | In Progress |